Building materials factory

Heat customer introduction

 

 

  • Terracotta building bricks production site
  • 180,000 tonnes/year production

 

Principle of solar thermal integration

 

  • Preheating of air for the drying process
  • Integration of a water/air exchanger into the main air inlet
  • Fossil fuel saved: gas

 

Key innovation

 

  • Complementary to gas co-generation systems already in place

 

Project key figures

December 2020

targeted work initiation date

9,800 m²

solar thermal collector area on trackers

3,000 m³

hot water storage volume

about 6,000 MWh

expected annual production

1,500 tonnes

of CO2 emission avoided per year

Category
Industry, Study case